any how i can set a limit Auxiliary copy jobs, once fist 5 jobs get copied then only next copy job should start. Using stand alone tape library

  • 17 August 2021
  • 2 replies
  • 153 views

Badge

lets say there are 1000 jobs needs to move on tape, i want to take the secondary copy of jobs on date wise it should not pic random jobs for aux copy.

icon

Best answer by Mike Struening RETIRED 17 August 2021, 15:29

View original

2 replies

Userlevel 7
Badge +23

@Rajesh Kumar , it is likely picking jobs based on stream usage on the Primary side.  Let me check internally if we can alter this behavior.

Userlevel 7
Badge +23

Here you go:

https://documentation.commvault.com/commvault/v11/article?p=11506.htm

You can change the Priority of what the Aux Copy selects.