The DDB Verification Job is scheduled to run an Incremental Verification of existing jobs on disk and dedup database, but Incremental data verification job is persistently converted to full. Why? 

 

 

 

Hello @Eduardo Braga 

The screenshot doesn’t indicate if the jobs are full or incremental. Can you open up the properties of one of them and share a screenshot?

 

Thank you,

Collin


Hello @Eduardo Braga 

The screenshot doesn’t indicate if the jobs are full or incremental. Can you open up the properties of one of them and share a screenshot?

 

Thank you,

Collin

 

CS FR 11.26.3


The Verification Type shows INC, thats looks good, where do you see it saying it converted to FULL. Let me know if I missed something


The Verification Type shows INC, thats looks good, where do you see it saying it converted to FULL. Let me know if I missed something

 

 

 