I need to create a schedule to data verification to copy that go to tape library ,

I saw this option in the commcell console,

I see option of all picked jobs in the advanced option of the data verification of the storage policy 

but I don’t see option of all the jobs that automatically go to the tape.

I can do ctrl A and select all the jobs is the storage policy copy and checkbox pick for verification

 

 

 

thank you very much!

 

Hello @ariel_b ,

Thank you for reaching out to us on this question!

Based on the screenshot provided, it appears that you may not have enabled Data Verification on the copy writing to tape.  Please make sure you have the copy enabled for DV before attempting to select media.

https://documentation.commvault.com/2023e/expert/getting_started_with_data_verification.html

Regards,

Josh P


Hello ariel_b,

To configure the verification,

  1. Go to Copy Properties->Advanced. Select the Data Verification checkbox.
  2. Then you can run the Data Verification from the Storage Policy level, and select the specific copy
  3. To schedule, go to the Job Initiation tab and you can select to create a schedule here

Hope this helps!


Hello,

I tried to schedule data verification and I did not see jobs that verified , I think I need to select  manually all the jobs for pick for verification.

and after that the verification will verify the data that go to tapes .

Thank you very much 


@ariel_b for this 

but I don’t see option of all the jobs that automatically go to the tape.

You can pick the copy which is using tape library and pick jobs on that copy.

 