Dear Team,

 

We have recently deployed a Tape library and configured secondary backup copies to tape. Now, we need to validate whether all backed-up copies onto tape are valid as part of the data integrity check.

What options are available to verify that the data available on tape is valid? Additionally, if ransomware affects my entire COMM server and Media agent, how can we recover using tape copies?

 

Regards,

ManiD 

Best answer by ManiD

Dear @SMD , thank you so much for your support.

View original
Did this answer your question?

10 replies

Forum|alt.badge.img+9
  • Vaulter
  • 125 replies
  • March 7, 2024

Hi @ManiD 

 

You can refer to below documments for Data Verificatrion:

Data Verification (commvault.com)

Getting Started with Data Verification (commvault.com)

 

Additionally, if ransomware affects my entire COMM server and Media agent, how can we recover using tape copies?

=> Is this case we will have to recover from CSDB and then restore data from Tapes.

=> You can refer to the below document for more details

CommServe Recovery Using Disaster Recovery (DR) Backups (commvault.com)

 

 

Regards,

Suleman

 


Forum|alt.badge.img+5
  • Author
  • Byte
  • 18 replies
  • March 7, 2024

Dear @SMD, Thanks for sharing the documents.

 

I will enable and schedule data verification for each copy. What is the best practice: daily, weekly, or monthly scheduling? Additionally, what are the benefits of performing data verification jobs?

 

Regards,

ManiD


Forum|alt.badge.img+9
  • Vaulter
  • 125 replies
  • March 7, 2024

Hi @ManiD ,

 

Data verification helps to validate and check data integrity once it is written to media.

 

To run it your call, defult schedule runs every day.

 

Regards,

Suleman

 


Forum|alt.badge.img+5
  • Author
  • Byte
  • 18 replies
  • March 8, 2024

Dear @SMD,

I have enabled data verification for all copies associated with the storage policy. After manually initiating a Run data verification process on the storage policy and completing the verification jobs, I observed the data verification status on each copy and the date of the last verification.

Do we need to schedule daily data verification for upcoming backup copies, or will data verification automatically occur alongside the backup process?

What is the best practice for managing the expiration of data verification? Thank you.

 

Regards,

ManiD

 

 


Forum|alt.badge.img+9
  • Vaulter
  • 125 replies
  • March 8, 2024

Hi @ManiD ,

 

Do we need to schedule daily data verification for upcoming backup copies, or will data verification automatically occur alongside the backup process?

=> Data Verification will run automatically based on the schedule

 

What is the best practice for managing the expiration of data verification ?

=> Data Verification status does not expire.

 

Regards,

Suleman


Forum|alt.badge.img+5
  • Author
  • Byte
  • 18 replies
  • March 10, 2024

Dear @SMD

=> Data Verification will run automatically based on the schedule. 

 

While creating a data verification job from the storage policy level, there is an option to schedule it and provide frequency details and policy name. However, I am unable to find the one which I was was created. Is it possible to have multiple storage policies data verification job with a single schedule policy?

Regards

ManiD


Forum|alt.badge.img+9
  • Vaulter
  • 125 replies
  • March 11, 2024

Hi @ManiD ,

 

is it possible to have multiple storage policies data verification job with a single schedule policy?

=> Yes it is possible, we need to associate it

 

Also, it is possible to have multiple shedules for a Storage Policy.

 

Regards,

Suleamn 


Forum|alt.badge.img+5
  • Author
  • Byte
  • 18 replies
  • March 12, 2024

Dear @SMD,

 

  1. I have created a data verification schedule policy, but I am unable to find the one which I created.
  2. Also, the primary backup is running full backups on Wednesday and Friday, and incremental backups on the other days (Saturday, Sunday, Monday, Tuesday, and Thursday). My requirement is for full backups to be taped: Wednesday's backup to one tape and Friday's backup to another tape.

Could you please assist me with this.

 

Regards,

ManiD


Forum|alt.badge.img+9
  • Vaulter
  • 125 replies
  • March 12, 2024

Hi @ManiD ,

 

=> Newly created Schedule will have a name and hence I cannot help you. you will have to filter schedule by type and then check associations.

 

Also, the primary backup is running full backups on Wednesday and Friday, and incremental backups on the other days (Saturday, Sunday, Monday, Tuesday, and Thursday). My requirement is for full backups to be taped: Wednesday's backup to one tape and Friday's backup to another tape.

 

=> then you will have to create 2 selective copies one with option “weekly full | First full backup” and another with option “weekly full | Last full backup” 

 

Regards,

Suleman

 

 

 


Forum|alt.badge.img+5
  • Author
  • Byte
  • 18 replies
  • Answer
  • March 13, 2024

Dear @SMD , thank you so much for your support.


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings