Hello everyone,
I have some VMs that are being protected, and for these VMs, a Plan was created for them (as we are MSP, and each VM has a specific schedule, a specific Plan was created to protect them) and the Plan was associated for them.
With this, two of the VMs it was necessary to configure the DR, and a Replication Group was created as should be, and the VMs was associated with this Replication Group.
I know that for the Disaster Recovery work needs to perform a backup job first in the source and with this backup job update the destination. Still, one thing came to my mind looking at this scenario: What happened with the Plan I created and associated before? The backup will be running as expected or only the DR? Also, after creating the Replication Group, both VMs are in this Replication Group, and I cannot manage the Plan as I can do with the other VMs in Command Center.
Does anyone have any idea about this?
Thanks, 😊.