Skip to main content
Question

Incremental DDB Verification Job converted to Full

  • February 1, 2023
  • 4 replies
  • 104 views

Forum|alt.badge.img+9

The DDB Verification Job is scheduled to run an Incremental Verification of existing jobs on disk and dedup database, but Incremental data verification job is persistently converted to full. Why? 

 

 

 

4 replies

Forum|alt.badge.img+14

Hello @Eduardo Braga 

The screenshot doesn’t indicate if the jobs are full or incremental. Can you open up the properties of one of them and share a screenshot?

 

Thank you,

Collin


Forum|alt.badge.img+9
  • Author
  • Novice
  • February 1, 2023

Hello @Eduardo Braga 

The screenshot doesn’t indicate if the jobs are full or incremental. Can you open up the properties of one of them and share a screenshot?

 

Thank you,

Collin

 

CS FR 11.26.3


Hyder
Vaulter
Forum|alt.badge.img+8
  • Vaulter
  • February 1, 2023

The Verification Type shows INC, thats looks good, where do you see it saying it converted to FULL. Let me know if I missed something


Forum|alt.badge.img+9
  • Author
  • Novice
  • February 2, 2023

The Verification Type shows INC, thats looks good, where do you see it saying it converted to FULL. Let me know if I missed something